An Update On The Build

We are thrilled to say that construction of KEFITA is on track to be completed by 2023. We have completed fourth-floor slab work and column reinforcement, plus formwork and props are underway for the fifth floor. This means we’re starting to get a real feel for the incredible 360 degree views our residents will enjoy […]
Kefita Rising – September 2021 update

Build progress is right on track with all parking floors now complete and the unique KEFITA floor now under construction. The KEFITA floor is the first of its kind in an Addis apartment building, offering luxury, Western-style facilities to residents and their guests, including a gym, meeting and work spaces, and a coffee lounge.
Kefita is rising…

KEFITA has come out of the ground! Our contractor Hua Hong Construction PLC has completed the construction of the foundation, retaining walls, basement and first floor slab. Despite a nationwide cement shortage, we are thrilled that construction has been able to stay on track. Thorough quality and strength tests ensure compliance to European, British and […]
Excavation complete

[fusion_builder_container hundred_percent=”no” equal_height_columns=”no” menu_anchor=”” hide_on_mobile=”small-visibility,medium-visibility,large-visibility” id=”” background_color=”” background_image=”” background_position=”center center” background_repeat=”no-repeat” fade=”no” background_parallax=”none” parallax_speed=”0.3″ video_mp4=”” video_webm=”” video_ogv=”” video_url=”” video_aspect_ratio=”16:9″ video_loop=”yes” video_mute=”yes” overlay_color=”” video_preview_image=”” border_color=”” border_style=”solid” padding_top=”” padding_bottom=”” padding_left=”” padding_right=”” type=”legacy”][fusion_builder_row][fusion_builder_column type=”1_1″ layout=”1_1″ background_position=”left top” background_color=”” border_color=”” border_style=”solid” border_position=”all” spacing=”yes” background_image=”” background_repeat=”no-repeat” padding_top=”” padding_right=”” padding_bottom=”” padding_left=”” margin_top=”0px” margin_bottom=”0px” id=”” animation_type=”” animation_speed=”0.3″ animation_direction=”left” hide_on_mobile=”small-visibility,medium-visibility,large-visibility” center_content=”no” last=”true” min_height=”” […]
Borehole complete

Our drilling contractor EDIT PLC completed and capped the Kefita proprietary water well which will serve the building. The well extends to 272.10 meters deep. Excellent Aquifers have been encountered and the well configuration is designed to maximise flows. All works have been overseen by our consultants, Eclipse Engineering PLC.
Integration meeting

Detailed design, mechanical, electrical and plumbing integration. Dawit Solomon, Managing Partner, BIGAR, leads the team through one of many rigorous work streams required in order that the complicated and detailed task of integration servesboth form and utility.
We’ve found our plot

After an extensive search across central Addis Abeba we have located a plot. Situated in the off Embassy Row in the Signal district of Addis, the site extends to 2300m2.